Sim Date 01.17.293
Population 382,314
I have experienced a power warning. I have two Power Plants
(both are hydrogen and both are getting old and expensive to use).
The North Plant
Cost $17,076
Condition 60%
Actual capacity 33071Mwh/mo
Actual Usage 28596 Mwh/mo
Capacity used 86%
Cost per Mwh $.46
The South Plant
Cost $19,948
Condition 42%
Actual capacity 23,550 Mwh/mo
Actual Usage 20,363 Mwh/mo
Capacity used 86%
Cost per Mwh $.71
Buying Power from:
City of Industry North 6,000 Mwh $1446
Cost per Mwh $.24
Selling Power to:
Centertown 4000 Mwh $2391
Price per Mwh $.60
East Centertown 9000 Mwh $5708
Price per Mwh $.63
North Western town 2000 Mwh $1201
Price per Mwh $.60
I am way to greedy to stop selling power that I’m buying cheaper than I’m selling it for!
So for a quick fix I bought more Power From:
City of Industry South 3,012 Mwh $829
Cost per Mwh $.28
Apx. Power Capacity 65,000 Mwh/mo
Apx. Current Power use 58,000 Mwh/mo
I can’t buy anymore power. I can sell 2000 more Mwh
I may get greedy, build a new power plant and sell more power???
I’ll need a new plant soon anyway.
It may even take care of my $9800 budget deficit